GE delivered only six engines to HAL in the last fiscal which ended Tuesday, short of the 11 promised as per the revised timeline.
theprint.in
Only six engines have been delivered to HAL in the last fiscal which ended Tuesday, short of the 11 promised as per the revised timeline.
Confirmation on the sixth engine came as ThePrint reached GE to inquire about the delay. “GE Aerospace has handed over the sixth F404-IN20 engine against the order from 2021. GE Aerospace and HAL continue to work closely to ensure clear line of sight of production schedules for the F404 engines,” read a statement by a spokesperson for GE Aerospace.
HAL sources said they have yet to receive the sixth engine in India, adding that the handover could have taken place in the US.
Sources in the defence establishment said GE has informed HAL that the delay in deliveries is due to the ongoing US-Israel and Iran war.
Earlier this year, ThePrint had reported that despite what the HAL claims, the first lot of the Tejas Mk1A, which was to be delivered to the Indian Air Force (IAF) in March 2024,
is likely to be inducted latest only by June-July this year—after a delay of over two years.
Incidentally, the IAF and the Ministry of Defence (MoD) have agreed to grant HAL certain exemptions from contractual obligations, so that the long-pending delivery of the Tejas Mk1A can start early this fiscal year. Under the new understanding, IAF will accept the aircraft if the Aeronautical Development Agency (ADA) and HAL complete the missile-firing tests, integration of radar to the electronic warfare systems, and the weapons package.
It is learnt that firing trials are complete and the certification process is underway. The three tasks were described as “completely essential” under the new arrangement.
HAL has argued before the defence ministry and IAF that much of the pending work is being overseen by ADA, and is not a manufacturing delay.
Major capabilities incorporated are undergoing the certification process and should be completed by the end of April. Following this, the IAF will undertake acceptance trials, which could last a few weeks.
NEW DELHI: With the Tejas Mk1A programme mired in persistent delays, Hindustan Aeronautics Limited (HAL) and the Indian Air Force (IAF) are set to hold a critic
www.newindianexpress.com
With the Tejas Mk1A programme mired in persistent delays, Hindustan Aeronautics Limited (HAL) and the Indian Air Force (IAF)
are set to hold a critical programme review later this month to take stock of progress and finalise a revised induction timeline, it is learnt.
Sources in the defence establishment said senior officials from the IAF and HAL will meet in New Delhi to assess the progress made on mandatory operational requirements, benchmarks considered non-negotiable for the aircraft to be accepted into service.
“
The outcome of the review will be decisive. If the programme is sufficiently on track, the IAF is likely to take delivery of the first Mk1A within the next two-three months. If not, further slippages are likely,” the source said.
The mandatory requirements include completion of missile firing trials, integration of the radar with the electronic warfare suite and validation of the full weapons package.
“The IAF is pushing for clarity on when the first aircraft, already over two years behind schedule, will finally be inducted,” the source added. “We have granted certain exemptions from contractual obligations and if the mandatory requirements are met, we would take the fighter as soon as possible.”
In February, HAL declared five Mk1As ready for delivery, saying the aircraft had incorporated “major” contracted capabilities. However, sources indicate that while the five aircraft described as “ready” incorporate key contracted capabilities,
not all contracted capabilities have yet received certification, with certain mandatory clearances still pending.