ISRO Small Satellite Launch vehicle (SSLV) : Updates

Foundation Stone Laid for Launch Pad at SSLV Launch Complex (SLC), Kulasekarapattinam

August 29, 2025
1756540143207.png

The SSLV Launch Complex is being established as a dedicated launch complex at Kulasekarapattinam, Tuticorin Dt., Tamil Nadu, in order to meet the growing launch demands of the country, primarily for SSLV launches and for the launch activities of Non-Governmental Enterprises (NGEs). Honourable Prime Minister had earlier laid the foundation stone for the SSLV Launch Complex on February 28, 2024 from Tuticorin. Since then, construction has been progressing for 32 out of the 33 major facilities. On August 27, 2025, Dr. V. Narayanan, Chairman, ISRO / Secretary, Department of Space laid the foundation for the Launch Pad at the SSLV Launch Complex (SLC). The SLC consists of stage preparation & vehicle integration buildings, launch pad & rail track systems, range systems, checkout systems, telemetry & tele-command systems, safety & firefighting facilities, and general civic amenities. Major systems including the Mobile Launch Structure (MLS), bogies, platforms, doors, Jet Deflection Duct and vibration isolation systems have been designed by SDSC SHAR. Major range systems such as radars, telecommand, and telemetry are being developed in-house and being realised through industry partnerships, with support from other ISRO centres including VSSC, SAC, ISTRAC and IISU.

1756540159984.png

On this occasion, the Shri Padmakumar E.S., Director, SDSC- SHAR; Shri Rajarajan A., Director, VSSC; and Shri J. Asir Packiaraj, Director, IPRC were present, along with senior officials of ISRO and State Government Officials.

The Second Launch Complex at this site is targeted for completion by the end of 2026, enabling launches of SSLV as well as rockets from NGEs. The launch of sounding rockets for upper atmospheric studies and demonstration of technologies is targeted to commence from December 2025.

Foundation Stone Laid for Launch Pad at SSLV Launch Complex (SLC), Kulasekarapattinam


1756540254179.png
1756540268399.png
1756540284639.png
 
  • Love
Reactions: TARGET
ISRO conducts Ground Test of SSLV Third Stage

December 30, 2025

ISRO carried out a successful static test of an improved version of the third stage (SS3) of Small Satellite Launch Vehicle (SSLV) on December 30, 2025 at the Solid Motor Static Test Facility of Satish Dhawan Space Centre, Sriharikota.

SSLV is a three stage all-solid launch vehicle developed by ISRO which is amenable to industrial production and can meet launch-on-demand with quick turn-around time between launches. The upper stage or third stage solid motor delivers as high as 4 km/s velocity to the launch vehicle and employs a monolithic composite motor case and a free-standing nozzle divergent to limit the stage inert mass.

The static test validated an improved version of the SS3 stage with a Carbon-epoxy Motor case, which has significantly reduced the mass of the stage, thereby improving the payload performance of SSLV by 90 kg. The stage also features an improved design for the igniter and nozzle system making the system more efficient and robust. The nozzle control is implemented through a fault-tolerant electro-mechanical actuation system with low power control electronics. The high-strength carbon filament wound motor case was realized at the Composites Entity of Vikram Sarabhai Space Centre, ISRO and the solid motor was cast at the Solid Motor production facilities at Satish Dhawan Space Centre, ISRO.

The motor was instrumented with around 233 measurements to capture parameters namely pressure, thrust, temperature, and vibration and control electronics and actuators parameters. All the measured parameters are observed close to predictions over the test duration of 108 seconds. With this successful static test firing test, improved version of SS3 motor is qualified for induction in flight.

In this year, multiple facilities have been commissioned in the country to enhance the capacity of realizing solid motors for the space programme. In July 2025, Solid Motor production facilities were commissioned at Sriharikota for augmenting the capacity. A second production line for Ammonium Perchlorate was commissioned in September 2025 at the Ammonium Perchlorate Plant at Alwaye to double the production capacity of Ammonium Perchlorate required for the processing of solid motors. An indigenous 10-tonne vertical mixer for the solid motor production line was commissioned this year at SDSC, which is the world's largest solid propellant mixing equipment.

The Solid Motor Production & Static Testing facilities at SDSC have also realized & static tested the solid motor for the first orbital launch of a launch vehicle developed by an Indian Space Start-up.

1767124307090.png
SS3 Motor at Test Bed

1767124317835.png
SS3 Motor Static Firing at Test Bed

ISRO conducts Ground Test of SSLV Third Stage
 

SSLV's 4th flight may be called SSLV-D4, not L1.​


SSLV has underwent considerable amount of interations and improvements since it's third developmental flight in 2024.

In December 2025, ISRO carried out a successful static test of an improved version of the third stage (SS3): Read more

In August 2026, ISRO tested improved version of the first stage of SSLV: Read more

Due to all these interations, ISRO has decided to treat SSLV's fourth flight as a developmental flight.

Source
 
Last edited:
ISRO aims to end the year with first operational launch of SSLV

The space agency cut down on its planned launches this year following the back-to-back failures of PSLV

Written by: Anonna Dutt
Delhi
Updated: Nov 25, 2026 03:57 AM IST
1795577363770.png
ISRO Chairman V Narayanan addresses the gathering during the 5th India International Space Conclave, in New Delhi on Tuesday. (ANI Photo)

THE INDIAN Space Research Organisation (ISRO) is set to end the year, which saw fewer missions following the back-to-back failures of its workhorse PSLV, with a key mission — the first operational launch of SSLV.

“We are aiming to launch another SSLV mission in December,” confirmed a senior ISRO official. The space agency needs to carry out two successful development missions before a launcher is declared operational. It has already carried out three development flights of SSLV so far, with the first one, on August 7, 2022, falling short of placing the satellites in the intended orbit. The second and the third development flights, in February 2023 and August 2024, were declared successful.

ISRO may also see another launch of its workhorse PSLV with a modified third stage soon, hinted ISRO chairman V Narayanan on the sidelines of the recently concluded India International Space Conclave.

“We have already conducted one ground test and will be ready to launch the PSLV after another ground test,” he told The Indian Express. The space agency conducted the first ground test after making the requisite changes following the failures of PSLV C-61 in May 2025 and PSLV-C62 in January 2026. Both missions failed due to anomalies in the third and the uppermost stage of the rocket. According to ISRO, the reasons behind the failure of the two missions were different.

After the failures, the third-stage configuration was revisited comprehensively and changes were made with respect to design margins, raw material acceptance criteria, assembly procedures, and quality checks that followed. The design was strengthened and essential improvements were also made to the nozzle configuration.

The Indian Express on Monday reported that the launch of the privately built PSLV-N1 may have to wait until after the launch of ISRO’s own PSLV. Narayanan on Tuesday said the industry built PSLV will be launched in the first quarter of 2027.

As against a planned 17 launches for FY 2026-27 — including at least four PSLV and five SSLV missions — as per ISRO’s annual report, the space agency was able to achieve only three launches this year, including the failed PSLV-C62. The space agency launched the earth observation satellite EOS-5 in September and much-awaited navigation satellite NVS-03 in October, bringing the country’s navigation system back online.

https://indianexpress.com/article/i...-december-pslv-modified-third-stage-10977044/

IN-SPACe to make advance payments non-refundable for rocket launches after customers pull out of SSLV mission

IN-SPACe chairman Pawan Goenka said the upcoming SSLV launch will carry only two satellites weighing around 60 kg each, despite initial demand exceeding the rocket's 350-400 kg capacity.

AIHIK SUR
NOVEMBER 24, 2026 / 17:15 IST
1795577495766.png
IN-SPACe chairman Pawan K Goenka

The Indian Space Promotion and Authorisation Centre is set to charge customers non-refundable, advance money for flights aboard rockets like Indian Space Research Organisation's (ISRO) Small Satellite Launch Vehicle (SSLV), chairman Pawan K Goenka said on November 24.

This is after many prospective customers for the upcoming SSLV launch scheduled at the end of the month, backed out at the last moment leaving the rocket to fly nearly empty, Goenka said on the concluding day of India International Space Conclave in New Delhi.

"If you take the launch that is happening at this month of SSLV. We had overflowing demand. The total capacity (of the rocket) is 350 kg - 400 kg and we had 500 kg of demand," Goenka said.

However, when time came for finalisation, everyone backed off. "But when we are going to be launching, there will only be two satellites (of around 60 kgs each) going. Everyone pulled back, saying I am not ready," Goenka said.

In a stern message to the industry, Goenka said, "Next time we are not going to allow that. We are going to charge you in advance, non-refundable. Because the rocket is going to go up empty."

This example came as part of a larger message to the industry that IN-SPACe is going to become a lot more stricter in the future, as opposed to the flexibility it offers the industry currently.

"We would at some point become more difficult and not accept this kind of flexibility. We are doing it today because we want to give that initial momentum to the country," Goenka said.

Goenka also reiterated on the need for the country to generate "heavy demand" in the space sector. "Demand is the elephant in the room," the automotive-turned-space industry veteran said.

Goenak said that Central and State governments are increasingly looking at space applications. IN-SPACe, he said, is also talking to "non-space" companies, and apprising them how space technology can be useful for them.