Maybe more P8I NeptunesWhat do the high chief visit achieve? more ISR options like uav or pleading for weaponisation case?
huh so soon? could be for our SSBNs no?2 SSNs?
For upgraded SSKs, most likely Type 209.2 SSNs?
ohhh wait we got a update on the p75I.![]()
New ships: Navy to break own records
At present, the duration of warship construction has been reduced to 31 months as opposed to 55-60 months in the past| India Newswww.hindustantimes.com
![]()
New ships: Navy to break own records
At present, the duration of warship construction has been reduced to 31 months as opposed to 55-60 months in the past| India Newswww.hindustantimes.com
A build time of 31 months would put us on par with Japan and SoKo. Shishir Gupta doesn't mention the tonnage either. Iirc, it took ~7 yrs for INS Nilgiri to be commissioned and that too with modular construction tech.
The 43,000 crore figure is from when the RFI was 1st issued. The actual figure is likely to be around 60,000+ crore.ohhh wait we got a update on the p75I.
The Indian Navy is acquiring submarine deterrence with Project 75 I (air-independent propulsion or AIP) submarine set to sign this financial year.
Price negotiations are currently underway and the government has set aside some ₹42,968 crore for acquisition of six submarines to be constructed at Mazagon Dockyards Limited with AIP being provided by German firm ThyssenKrupp Maritime Systems.
The article doesn't say whether build time is 31mo from keel laying to delivery or launch to delivery. So I can't make a fair assessment.thats quite normal for first of class ships. IF you take Mahendra giri for example the keel was laid on 28th june 2022 and it will be commisioned by next year. Thats four years or about 48 months.
Compare that to the mogami class which is nearly 1000 tonnes lower and was underbuilt from their initial plans. they only have about 16 VLS cells and hell the first six ships were commisioned without their VLS cells. this is the reason they maintained a 30 month keel to commision rate. only from the 7th ship onwards did ships come with their 16 mk41 VLS cells from the start.
We can improve massively with our own navy building and are actively improving with a large amount of private shipayrds also stating to be involved in defence manufacturing but we are not so bad lol. We do need to improve massively though to even hope of a chance to compete with china in the IOR let alone outside it.
P17A was also the first time we did modular construction at that scale so the delay was anticipated since we need to break in but now the keel to commsion times for the p17B will be a lot lower since It shares a lot of hull characteristics with the p17A class and we have decent expertise in modular construction. It takes time to build a competent industry and we are starting to see the initial fruits of the labor today
taragiri also just got delivered so we might get a late dec early jan commisioning, mahendragiri and dunagiri should also be ready by q1 2026 so by arpil ish we should have at least 1 more commisioned and 2 more delivered if not commisioned. Vindhyagiri by the end of that year(oct ish as well).• List of Naval vessels commissioned till November, 2025 in the Indian Navy (11):
01. INS Vagsheer (P-75) - January 15, 2025
02. INS Surat (P-15B) - January 15, 2025
03. INS Nilgiri (P-17A) - January 15, 2025
04. INS Arnala (ASWSWC) - June 18, 2025
05. INS Tamal (P11356) - July 1, 2025
06. INS Udaygiri (P-17A) - August 26, 2025
07. INS Himgiri (P-17A) - August 26, 2025
08. INS Androth (ASWSWC) - October 6, 2025
09. INS Nistar (DSV) - July 18, 2025
10. INS Ikshak (SVL) - November 6, 2025
11. INS Mahe (ASWSWC) - November 24, 2025
• List of decommissioned vessels (2):
01. INS Abhay (ASW) - October 6, 2025
02. INFAC T-82 (FAC) - October 6, 2025